Hayriye Yonat
Silivri, Istanbul
2019
Industrial
Delivered under a fixed-price contract in nine months, this industrial facility exemplifies disciplined project management — combining a BIM-based cost model, bulk steel procurement at a price trough, and parallel construction scheduling to meet both budget and programme targets without compromise.
Project Challenges
Under a fixed-price contract it was necessary to deliver the industrial building on time and within budget while meeting TS EN ISO construction standards. Steel price volatility during this period made supply chain management a critical variable.
Our Solutions
A BIM-based cost model enabled proactive budget monitoring throughout design. Steel procurement was placed as a bulk order at a price trough; parallel scheduling of prefabricated panel cladding and floor works saved three weeks on programme. The building was ready for permit inspection ahead of the target date.
Driven by our love for people and the environment and respect for our craft, we have been providing architectural and contracting services since 2010.